Vol. I — No. 1Morgan Hill, CaliforniaTuesday, November 3, 2026
The Llagas Creek Gazette
All the news from 18231 Llagas Creek Dr — the work, the money, and what happens next.
The Property
18231 Llagas Creek Dr
Morgan Hill, CA 95037
Stage
Pre-listing preparation
No list price or date yet — the house is being made ready.
The Sellers
Dave, Ron & Emile Dell’Aquila
Co-sellers — every spend takes all three.
Listing Agent
Kay Korbel
Realty Experts — she gathers the vendors, invoices and bids, and reports to the brothers. Most of what’s printed here comes from her reports.
A House Gets Ready: Rodents First, Then Everything Else
From Kay Korbel’s reports to the sellers, late September – November 3, 2026
The Llagas Creek house is being readied for sale, and the work has a strict order to it. Kay’s sequence: the house must be cleared of rodents first — fumigation can’t happen until it is — then fumigation, the Section One pest repairs, the plumbing repairs, exterior paint, interior paint, cleaning, staging, and at last photography. No asking price or list date has been set; this paper exists to keep the record straight while the house gets there.
The biggest job so far is done and paid: Silicon Valley Rodent Proofers’ $5,800 proofing of the roof vents, eaves, attic and crawl space was invoiced October 18 and marked paid. But “paid” isn’t “finished” — the trappers keep checking until the house is clear, and Kay was still chasing that confirmation on October 29. Everything downstream waits on it: the signed $1,020 of extra crawl-space work at Clean Crawl Space is deliberately not scheduled yet, on Kay’s instruction, until the rodent crew clears the sub area and seals the entry points. Scheduling is expected in early December.
Money is moving in smaller pieces, too. Clean Crawl Space’s two October invoices — $1,125 for the sump pumps and $1,800 for pulling down the vapor barrier — were paid by Ron. Kay fronted $3,064.18 of early costs out of her own pocket. And her October expense plan projects $83,324.18 of third-party work all-in before the house is sold — paint, pest repairs, cleaning, staging and photography included.
Two bills need the brothers’ attention now. Nelson’s Pool shows $3,881 due for the new spa heater and monthly service — but Kay’s own instruction, from October 22, is to pay the heater only after Mike Nelson tests the system once the security spa cover is installed, expected mid-November. And the city water bill — $652.13, due November 10 — is not on autopay, whatever anyone remembers. It has to be paid by hand. Details in the boxes below.
§ Where Things Stand
The workstreams, one line each
Rodent proofing (Silicon Valley Rodent Proofers). Main $5,800 job invoiced and paid Oct 18 — and the house is now clear: Kay confirmed the infestation cleared when she briefed the plumbers on Nov 13. A further $375 invoice (#1774) for extra attic cleanup arrived Nov 3; no payment recorded yet. Kay has also asked Julio to investigate the dead attic fan — a critter may have damaged it.
Crawl space (Clean Crawl Space). Sump pumps ($1,125) and vapor-barrier pull-down ($1,800) done and paid by Ron. Extra work — 18 liner holes ($720) + an alarm wire ($300), $1,020 total — is signed by Ron and Emile; it was held until the rodent crew finished, which has now happened, so early-December scheduling stands. Structural engineer Sonny Vakul’s Nov 12 directive for the liner reinstall: leave 8–12 inches of the perimeter grade beam exposed, and check and seal any holes or tears. A separate $3,600 quote to reseal the liner awaits the brothers’ decision.
Plumbing — two bids in, decision pending. The inspection repair list (attic fan, Jack-and-Jill leak, water-heater strap, corroded gas pipe, garage sink wand, leaking hose bib) now has two live bids: Superior Plumbing, Estimate 3131 — $12,500 (Nov 13; Ron approved it that night; Kay agreed Nov 14 the work must be done, the gas line especially) and Michael Venosta Plumbing — $5,705 itemized (Nov 16; Dave’s referral — Mike has worked on the house before — and he has offered to remove the car lift at no cost). Decided Nov 17: the sellers are going with Venosta. Dave told Kay by text himself; Kay will schedule the work from there. Top Shelf’s earlier $4,493 estimate was never approved and has gone quiet. PG&E gas service is off at the house until the gas line is replaced; Kay will then arrange the turn-on.
Fumigation & termite repairs — done. Best Care’s second tenting ran Nov 9–11; HomeGuard’s pellet masking/removal followed on Nov 12, and HomeGuard’s Section One termite repairs are complete — Notice of Completion and Section One clearance sent Nov 12 (Report 682572), invoice with them (see The Money). A home + pest reinspection comes after the plumbing repairs.
Pool & spa (Nelson’s Pool Service). New Raypak spa heater installed; $3,881 balance presented Nov 1 — but see Kay’s pay-after-test condition in the flags below.
Paint (Platinum Quality Painting). Exterior $13,000 + $500 for gutters; interior $14,300. Painters were on site doing interior prep the week of Nov 16 (Kay, Nov 13–16).
Kitchen & lights (Kay’s Nov 14 expense update). Two bids are coming to replace the kitchen countertops and backsplash with quartz (sinks, faucets and disposals included in the bids). A light-fixture list is outstanding — interior lights, walkway pillar lights, the porch pair, patio and garage sconces. And a $415.63 Amazon wine fridge awaits the sellers’ keep-or-return vote.
Staging (Mayra Vera). $4,250 design/styling fee using the sellers’ own furniture. Undecided — and it gates what house contents can be sold, since staging borrows the furniture.
§ Waiting On — the Open Items
Plumbing — decided Nov 17: Venosta, $5,705. Dave made the call and told Kay by text himself today; no email follows — Kay schedules Venosta from his text. (Superior’s $12,500, which Ron had approved Nov 13, is not chosen.) Still ahead once the work is done: Kay arranges the PG&E gas turn-on — service stays off until the corroded gas line is replaced.
HomeGuard — handled (Nov 20). Section One termite repairs are complete; the statement balance was $23,989 (Report 682572). Dave confirmed on Nov 20 that it’s handled. No payer or method was specified, so the Gazette records it as handled, not paid — and the $225 DPA-fee waiver question went moot with the handling.
Nelson’s Pool, $3,881 (Invoice #4986) — presented as due, but Kay’s Oct 22 condition says the $3,741 heater is payable only after a successful test once the spa cover is on (~mid-November). The $140 monthly service is undisputed. No payment recorded yet.
SVRP Invoice #1774, $375 — additional attic cleanup, forwarded to the brothers Nov 3; $0 paid so far.
Wine fridge, $415.63 — keep or return? Kay bought a wine fridge on Amazon (her Nov 14 expense update) and can return it if the sellers don’t want the expense. The keep/return vote is still pending — Dave’s vote hasn’t been sent yet.
Quartz countertop bids — two bids coming to replace the kitchen countertops and backsplash with quartz (Carrara-look; sinks, faucets and disposals included). The brothers decide once the prices land.
Light fixtures — outstanding per Kay’s Nov 14 update: 3 interior lights; 2 small exterior lights on the walkway pillars; the 2 new porch fixtures (already at the house) to flank the front door; 3 patio sconces and 2 garage sconces to be replaced.
Liner decision — reseal the crawl-space liner for $3,600, or price a full replacement (unquoted, “much more”)? The brothers’ call — with Sonny’s Nov 12 reinstall directive (grade beam left 8–12″ exposed, holes and tears sealed) now on the record either way.
Clean Crawl scheduling — the signed $1,020 of extra sub-area work was held for the rodent all-clear; the house is now clear (Kay, Nov 13), so the early-December scheduling can proceed.
Staging, $4,250 — Mayra Vera’s proposal still undecided.
Reinspection — home + pest reinspection to be scheduled once the plumbing repairs are done (Kay’s plan, Nov 4).
Spa security cover — the Nelson heater test waits on it; purchase/install status unconfirmed.
Kay’s reimbursement — $3,064.18 she fronted as of Oct 6; reimbursement status not recorded. (Kay circulated an updated expense spreadsheet on Nov 14.)
House contents — the selling plan waits on the brothers and the staging decision. One exception is already moving: the vintage steel tanker desk is free on Marketplace and in this paper’s Free Stuff section below.
Editor’s flag — read the Nelson’s bill with Kay’s condition attached. Nelson’s November statement presents the full $3,881 as the balance due, due by the 26th. Kay’s October 22 instruction stands alongside it: the heater gets paid after it passes its test. Both facts are true; the Gazette prints them together so nobody pays the wrong one first.
Editor’s flag — the water mystery. The $652.13 bill itself is settled — paid Nov 10. The mystery isn’t: 114 hundred-cubic-feet of water ran through a vacant house in September, and no one has explained it yet. (An actively leaking hose bib by the garage is on the plumbing repair list — it may or may not be the answer.) Until somebody explains it, treat every future water bill as worth a second look.
§ The Money
Paid
Item
Amount
Silicon Valley Rodent Proofers — main proofing job (Invoice #1761)
$5,800.00
Clean Crawl Space — sump-pump servicing (#14637), paid by Ron
$1,125.00
Clean Crawl Space — vapor-barrier pull-down (#14644), paid by Ron
$1,800.00
MG Constructors — structural engineer (in Kay’s out-of-pocket below)
Sergio Gardening — hauling and extra work (Sep–Oct)
$2,450.00
Nelson’s Pool — spa repair (Invoice #4645)
$583.00
City of Morgan Hill water/sewer — Bill #421657, paid Nov 10 (payment completion notice that evening)
$652.13
Kay’s out-of-pocket as of Oct 6 — alarms, fixtures, fireplace inspections, Duke’s, inspections (includes the MG $1,350 above)
$3,064.18
Due / presented for payment
Item
Amount
Nelson’s Pool — Invoice #4986 (spa heater $3,741 + $140 monthly service) — heater payable after its test, per Kay
$3,881.00
SVRP — Invoice #1774, additional attic cleanup
$375.00
HomeGuard — Section One termite repairs (complete Nov 12; Notice of Completion & Section One clearance issued, Report 682572; statement balance $23,989) — handled per Dave, Nov 20; payer/method not specified, so it is recorded as handled, not paid
$23,989 — handled
Wine fridge (Amazon, bought by Kay; her Nov 14 expense update) — sellers’ keep-or-return vote pending
$415.63
Agreed, quoted, or planned — not yet paid
Item
Amount
Clean Crawl Space — signed sub-area work (liner holes + alarm wire), held for early December
$1,020.00
Clean Crawl Space — reseal liner (quote, undecided)
$3,600.00
Michael Venosta Plumbing — bid for the inspection repair list, itemized: attic vent fan $1,200 · Jack-and-Jill leak $1,365 · water-heater strap $105 · corroded gas pipe $2,450 · garage sink wand $510 · hose bib $75 (CA license #969247; bid forwarded by Kay Nov 16; approved by Dave Nov 17 — he told Kay by text himself, and Kay will schedule the work; includes an offer to remove the car lift at no cost)
$5,705.00
Superior Plumbing — Estimate 3131 for the same repair list (Nov 13; Ron approved Nov 13, Kay agreed Nov 14) — not chosen; the sellers went with Venosta on Nov 17
$12,500.00
Top Shelf Plumbing — Estimate #94, revised Oct 29 — never approved, no word since; superseded by the Superior and Venosta bids above
$4,493.00
Kitchen quartz countertops & backsplash — two bids coming (Kay, Nov 14); sinks, faucets and disposals included in the bids
awaiting bids
Platinum Painting — exterior + gutter cleaning
$13,500.00
Platinum Painting — interior
$14,300.00
Section One pest repairs + additional damage — work completed Nov 12 (HomeGuard; clearance issued) — the cost now sits in Due, on the HomeGuard invoice above, and this Oct 11 plan figure is retired
$23,705.00
House cleaning after painting (Martina Torres)
$3,000.00
Staging (Mayra Vera)
$4,250.00
Photography
$950.00
Garage concrete repair
$340.00
Kay’s projected third-party total (her Oct 11 expense plan; an updated spreadsheet followed on Nov 14)
Sep 29Kay sends the brothers Nelson’s spa invoice, the pest inspection report, and Mayra Vera’s $4,250 staging proposal.
Sep 30Structural engineer Sonny Vakul (MG Constructors) walks the house and the inspection reports.
Oct 2Duke’s Heating & Air invoice arrives: $575 total, $75 balance; Kay asks who should pay it. (Her own expense sheet later lists the $75 as paid by her.)
Oct 4A DocuSign envelope for Emile’s sale signature bounces — flagged as a blocker then; he later signs the crawl-space agreement fine on Oct 31, so the sale envelope’s status is simply unconfirmed.
Oct 7SVRP Estimate #787: $5,800 to screen, seal, clean and trap the house clear of rodents, with a one-year warranty.
Oct 8Revised paint bids circulate: Platinum exterior $13,000 + $500 gutters; interior $14,300; 10% deposits to schedule.
Oct 11Kay’s expenses package lands: projected third-party total $83,324.18, her $3,064.18 out-of-pocket, and the paid receipts.
Oct 14Clean Crawl Space inspects the sub area — the visit that produces the $1,020 work agreement.
Oct 16Clean Crawl Space invoices #14637 ($1,125) and #14644 ($1,800) forwarded to the brothers.
Oct 18SVRP Invoice #1761 for the $5,800 main job — marked paid.
Oct 19Vendor confirms Ron paid both Clean Crawl invoices. Kay asks Superior Plumbing for a competing bid (still outstanding).
Oct 22Kay forwards the $3,741 Raypak spa-heater invoice with her condition: pay after Mike tests the system post-cover, ~mid-November.
Oct 23The three brothers confer by phone — sign-offs, the water question, house contents. (Decisions from the call aren’t in the email record.)
Oct 27Kay sends Top Shelf the inspection repair list; Estimate #94 comes back that night at $5,617. Ron reports fixing the garage spray wand himself — calcification — though hose and sprayer still go on the list.
Oct 28Kay pushes back on Top Shelf’s price; Ray offers 20% off. Best Care Fumigation sends its prep forms. Clean Crawl quotes $3,600 to reseal the liner.
Oct 29Revised Top Shelf estimate: $4,493. Kay tells the brothers the plumbing can wait until after fumigation and paint, and that she’ll chase the rodent all-clear — “critical that the house be free of rodent prior to fumigation.”
Oct 30–31Ron (Oct 30) and Emile (Oct 31) DocuSign the Clean Crawl Space work agreement.
Nov 1Nelson’s Invoice #4986: balance due $3,881 (heater + monthly service), payment asked by the 26th.
Nov 2Kay sends Clean Crawl Space the signed $1,020 work order with a bold instruction: do not schedule yet — early December, after the rodent crew clears and seals.
Nov 3Kay forwards SVRP Invoice #1774: $375 for additional attic cleanup. And this Gazette publishes its first edition.
Nov 4Kay’s group text to the brothers: a contractor’s bid on the inspection repair items is expected the week of Nov 9, and a second fumigation is set — tent on Mon Nov 9, off Wed Nov 11, HomeGuard pellet masking/removal Thu Nov 12, reinspection after the repairs. The tanker desk flips to free on Marketplace.
Nov 9–11Second fumigation: Best Care’s tent goes on Monday and comes off Wednesday.
Nov 10The city water bill is paid — $652.13, Bill #421657; the payment completion notice lands that evening. (It never was on autopay; a scheduled payment did it.)
Nov 12HomeGuard’s pellet masking/removal is completed, and Jeffrey Read sends Ron and Emile (Dave cc’d) the Notice of Completion, Section One clearance and invoice for the termite repairs (Report 682572) — the Section One work is done. The Notice carries a $225 DPA fee the sellers don’t owe if payment lands within five business days. The same day, structural engineer Sonny Vakul directs Clean Crawl Space on the liner reinstall: leave 8–12 inches of the grade beam exposed; check and seal holes and tears.
Nov 13Superior Plumbing’s Estimate 3131 lands: $12,500 for the repair list — more scope than first listed (walls opened in two places, a toilet flange rebuilt; 2–3 days, a multi-person crew). Ron approves it that night. Kay, briefing Dave’s referral Michael Venosta for a competing bid, confirms the rodent infestation has been cleared, the tent is off, and the gas is off at the house.
Nov 14Kay agrees the plumbing work must be done — the gas line especially — and notes PG&E gas service is off until the line is replaced, after which she’ll arrange the turn-on. Her updated expense spreadsheet lands: a $415.63 Amazon wine fridge (keep-or-return vote for the sellers), the outstanding light-fixture list, and two quartz countertop-and-backsplash bids on the way.
Nov 16Venosta’s bid lands: $5,705, itemized across all six repair items, with an offer to remove the car lift at no cost. With Superior’s $12,500 also on the table, the plumbing decision is Dave’s to make. The tanker desk also runs as a free item in this paper (Free Stuff, below).
Nov 17Decision: Venosta. Dave picks the $5,705 bid and tells Kay by text himself — no email; Kay will schedule Venosta from his text. Superior’s $12,500 is not chosen.
Nov 20HomeGuard: handled. Dave confirms the $23,989 statement (Report 682572) is handled. No payer or method specified — the paper records it as handled on his word, not as paid.
§ Free Stuff
Giveaways from the house — free to whoever picks them up. Added Monday, November 16, 2026.
FREE
Vintage Steel Tanker Desk
The desk, front view — woodgrain top, five drawers, chrome legs.Close-up: the left pedestal — chrome pulls, lock hole, honest wear.As first photographed at the house, October 21.
A heavy mid-century steel tanker desk, free to a good home. It measures 60″ long × 30″ deep × 30″ high. Double pedestal: on the left, a shallow drawer over a deep locking file drawer (the lock cylinder is there; a key is not confirmed); on the right, three drawers. Dark woodgrain laminate top, chrome pulls and legs. Solid and sturdy — built like a tank. The top is dusty, with light scuffs from storage.
Pickup: at the house, 18231 Llagas Creek Dr, Morgan Hill — you pick it up there, and bring help: it is genuinely heavy. First confirmed pickup takes it.
To claim it: message Dave through the Facebook Marketplace listing (also free there, with the same photos) and arrange a time. This notice also runs in the Fiddletown and Lenwood Gazettes.